Monaghan Street. The Monaghan Town Centre Regeneration Project which will see The Diamond, Dublin Street and Old Cross Square areas undergo a major environmental enhancement.

Read More

Projects

image

Glasough Street Monaghan

This project saw us extend phase 1 from where we stopped, right into the ‘diamond’, centre of monaghan town. As before we laid brick footpaths with granite kerbs either side of the road, dig out the existing road and laid new reinforced concrete slabs under the new tarmac road.

 

Story So Far

Overall the completion of this project took 8 weeks, 6 weeks for footpath completion and a road closure of 2 weeks.